During the terminal renovation, taxis are relocated and the administrative building will temporarily serve as a terminal.

Temporary Taxi Stand and Terminal in Administrative Building

In this phase of the Osijek Airport terminal reconstruction, temporary traffic regulations have been reorganized. The current taxi stand has been relocated in front of the airport’s administrative building, where five parking spaces are available for taxi vehicles due to the scope of construction works.

At the same time, preparations are underway to temporarily convert the administrative building into a terminal, as passenger processing will take place there for a certain period during the works. Construction on the terminal continues according to schedule. The most visible progress so far is the installation of a steel structure on the western and southern façades, clearly showing the future dimensions of the new facility.